PrepAway - Latest Free Exam Questions & Answers

Which schedule compression technique has phases or activities done in parallel that would normally have been d

Which schedule compression technique has phases or activities done in parallel that
would normally have been done sequentially?

PrepAway - Latest Free Exam Questions & Answers

A.
Crashing

B.
Fast tracking

C.
Leads and lags adjustment

D.
Parallel task development