which of the following?

The Cost Management processes and their associated tools and techniques are
usually selected during which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Project finance management

B.
Project cost estimation

C.
Project life cycle definition

D.
Project plan development