what Project Time Management process?

Activity resource requirements and resource breakdown structure are outputs from
what Project Time Management process?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule Control

B.
Activity Definition

C.
Schedule Development

D.
Activity Resource Estimating