The methodology that combines scope, schedule, and resource measurements to assess project performance and pro

The methodology that combines scope, schedule, and resource measurements to
assess project performance and progress is known as:

PrepAway - Latest Free Exam Questions & Answers

A.
Earned value management.

B.
Forecasting.

C.
Critical chain methodology.

D.
Critical path methodology.