Activity resource requirements and the resource breakdown structure (RBS) are
outputs of which Project Time Management process?

PrepAway - Latest Free Exam Questions & Answers

A.
Control Schedule

B.
Define Activities

C.
Develop Schedule

D.
Estimate Activity Resources