Status of deliverables, implementation status for change requests, and forecasted estimates to complete are ex

Status of deliverables, implementation status for change requests, and forecasted
estimates to complete are examples of:

PrepAway - Latest Free Exam Questions & Answers

A.
Earned value management.

B.
Enterprise environmental factors.

C.
Organizational process assets.

D.
Work performance information.