PrepAway - Latest Free Exam Questions & Answers

which would increase scope and possibly any related analysis costs?

Which of the following would be used to pay for an issue which would increase scope and possibly
any related analysis costs?

PrepAway - Latest Free Exam Questions & Answers

A.
Contingency

B.
Tolerance

C.
Change budget

D.
Risk budget