Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?

Which PRINCE2 principle supports planning only to a level of detail that is manageable and
foreseeable?

PrepAway - Latest Free Exam Questions & Answers

A.
Continued business justification

B.
Manage by exception

C.
Focus on products

D.
Manage by stages

One Comment on “Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?

  1. Sharifi says:

    that is right, because of
    2.4 Manage by stages:
    A PRINCE2 project is planned, monitored and controlled on a stage-by-stage basis.
    Planning can only be done to a level of detail that is manageable and foreseeable