Which product would the Project Manager use for gathering Work Package progress information?

Which product would the Project Manager use for gathering Work Package progress information?

PrepAway - Latest Free Exam Questions & Answers

A.
Highlight Report

B.
Daily Log

C.
Checkpoint Report

D.
Product Status Account