When would the Team Manager be required to produce a Checkpoint Report?
A.
When a Work Package is being negotiated
B.
At the frequency agreed in the Work Package
C.
On completion of the quality-checking activities for each product
D.
When reviewing how a stage is progressing
Correct answer is B.
0
0
i agree
0
0
“A” is wrong, and “peppe” is wrong in agreeing. The answer presented is correct. The Checkpoint report is used by the PM to review the progress. The progress is communicated to the project board at agreed intervals via the highlight report; and done so as per the intervals agreed and defined in the communication strategy.
0
0
I agree
0
0
Correct answer is “B”
See “Managing successful projects with PRINC2”
Page 238 – Appendix A: Product Description outlines
A.3 Checkpoint Report
A.3.1 Purpose
A Checkpoint Report is used to report, at a
frequency defined in the Work Package, the status
of the Work Package.