PrepAway - Latest Free Exam Questions & Answers

When would the Team Manager be required to produce a Checkpoint Report?

When would the Team Manager be required to produce a Checkpoint Report?

PrepAway - Latest Free Exam Questions & Answers

A.
When a Work Package is being negotiated

B.
At the frequency agreed in the Work Package

C.
On completion of the quality-checking activities for each product

D.
When reviewing how a stage is progressing

5 Comments on “When would the Team Manager be required to produce a Checkpoint Report?

  1. Rodrigo says:

    “A” is wrong, and “peppe” is wrong in agreeing. The answer presented is correct. The Checkpoint report is used by the PM to review the progress. The progress is communicated to the project board at agreed intervals via the highlight report; and done so as per the intervals agreed and defined in the communication strategy.




    0



    0
  2. d3m0 says:

    Correct answer is “B”

    See “Managing successful projects with PRINC2”

    Page 238 – Appendix A: Product Description outlines

    A.3 Checkpoint Report

    A.3.1 Purpose
    A Checkpoint Report is used to report, at a
    frequency defined in the Work Package, the status
    of the Work Package.




    0



    0

Leave a Reply