Which of the following would be done during the initiation stage?
A.
Appoint the Executive
B.
Establish who needs information, when and in what format
C.
Establish the quality expectations of the customer
D.
Define how the project will deliver the chosen business solution
I have the same idea. B
0
0
I think the answer should be C,
Customer Quality expectation is part of Project Product Description and it is created in IP Process.
Anyone please correct me?