What’s the purpose of the ‘Plan’ step within the risk management procedure?

What’s the purpose of the ‘Plan’ step within the risk management procedure?

PrepAway - Latest Free Exam Questions & Answers

A.
Create a Risk Management Strategy for inclusion in the Project Initiation Documentation

B.
Establish the Project Board’s specific risk management responsibilities and assign them as
owners of specific risks

C.
To plan the Communications Management Strategy in order to identify and capture any
external stakeholder risk information requirements

D.
To identify suitable management responses to be implemented to manage a risk, should the
risk occur