What is NOT an objective of the Directing a Project process?
A.
Ensure there is authority to deliver the project’s products
B.
Ensure that corporate or programme management has an interface to the project
C.
Provide sufficient information to enable the continuing viability of the project to be assessed
D.
Management direction and control are provided throughout the project’s life
I agree with the answer. C