C. When preparing a Project Brief during pre-project work
D. When authorizing the project
3 Comments on “When is the Risk Register created?”
Asays:
When preparing the Risk Management Strategy.
0
0
Jopicasays:
B is correct, see below:
In the initiation stage The Risk Management Strategy will be created to describe how risk management will be embedded within the project. At the same time, The Risk Register will be created and any risks currently within the Daily Log will now be transferred to this register.
When preparing the Risk Management Strategy.
0
0
B is correct, see below:
In the initiation stage The Risk Management Strategy will be created to describe how risk management will be embedded within the project. At the same time, The Risk Register will be created and any risks currently within the Daily Log will now be transferred to this register.
0
0
I agree with the answer. B