Which of the following would NOT be classified as a threat to a project?
A.
A competitor may launch a rival product first thus affecting the expected market share for the
product
B.
It is possible that the product completes user acceptance testing in a single test cycle rather
that the scheduled two
C.
A prototype may be damaged in transit
D.
A critical meeting could be affected by air travel disruption