Which is NOT established as part of the Starting Up a Project process?

Which is NOT established as part of the Starting Up a Project process?

PrepAway - Latest Free Exam Questions & Answers

A.
A Plan for the work of initiation

B.
Information on the various ways the project can be delivered

C.
A description of what the project is to deliver

D.
A plan for how and when a measurement of the achievement of the project’s benefits can be
made