What product is reviewed by the Project Manager as part of progress assessment to determine whether a Work Pac

What product is reviewed by the Project Manager as part of progress assessment to determine
whether a Work Package is performing to the agreed cost and time tolerances?

PrepAway - Latest Free Exam Questions & Answers

A.
Highlight Report

B.
Checkpoint Report

C.
Exception Report

D.
Off-specification