A stakeholder wishing to make an observation about the project would do what?
A.
Ask for it to be included in the Communication Management Strategy
B.
Raise an issue
C.
Make an entry in the Issue Register
D.
Arrange a meeting with a Project Board member
I have the same idea. B
0
0
yes because anyone who have interest in the project can raise an issue. wright?