Which theme assesses and controls uncertainty within a project?

Which theme assesses and controls uncertainty within a project?

PrepAway - Latest Free Exam Questions & Answers

A.
Progress

B.
Risk

C.
Change

D.
Plans

One Comment on “Which theme assesses and controls uncertainty within a project?

  1. Rodrigo says:

    The given answer is correct. Reference pg.77 Section 5.1 in “Managing Successful Projects with PRINCE2” 2009 Version. Also pg.22 in PRINCE2 for Dummies.