The creation of an Exception Plan often follows which situation?

PrepAway - Latest Free Exam Questions & Answers

A.
A time or cost slippage occurs during a management stage

B.
An Exception Report being submitted to the Project Board

C.
A Stage Plan is updated due to an urgent corrective action being taken

D.
An Issue Report being created