which product should be updated to reflect this?

If, at the end of each stage, circumstances external to the project had changed which affect the
project’s costs, risks and benefits, which product should be updated to reflect this?

PrepAway - Latest Free Exam Questions & Answers

A.
Exception Plan

B.
Project Plan

C.
Project Brief

D.
Business Case

5 Comments on “which product should be updated to reflect this?

  1. attitudedon says:

    The purpose of the Business Case is to set out the justification for the project.If the circumstances have changed, Business case must be updated for continued business justification. Later Project Plan can be updated accordingly or replaced with Exception Plan.

    So the answer should be D.

    Please anyone have idea, suggest.