Which process controls the link between the Project Manager and the Team Manager(s)?

Which process controls the link between the Project Manager and the Team Manager(s)?

PrepAway - Latest Free Exam Questions & Answers

A.
Controlling a Stage

B.
Managing a Stage Boundary

C.
Managing Product Delivery

D.
Directing a Project