Which of the following is a TRUE principle of a PRINCE2 project?
A.
Please refer to section 2.3 in the PRINCE2 Manual
B.
Work Package level activities are identified during Starting up a Project
C.
A project has defined and agreed roles and responsibilities
D.
Every project will need a different project management approach
Correct answer is C.
0
0
yes, correct answer is C
0
0
yes i agree,correct answer is C
0
0
From the two possible answers (B and C) the Answer is B. This is because both of them point to PRINCE2 principles. This isn’t apparent at first but if you look at B, it points to the “Focus on Products” principle. When the project products are defined, and their descriptions are properly, then the work is broken down into Work Packages. It is only after defining the work packages that the PRINCE2 principle of “Defined Roles and Responsibilities” can be applied.
0
0
My answer is wrong. for this I apologize.
The correct answer is C.
0
0
Thanks for all your comments. C is the correct answer I guess.
0
0
Yes, the correct answer is C.