During project initiation, who determines the use of a Change Authority and whether a change budget will be us

During project initiation, who determines the use of a Change Authority and whether a change
budget will be used?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Board

B.
Change Authority

C.
Project Manager

D.
Corporate or Programme Management

8 Comments on “During project initiation, who determines the use of a Change Authority and whether a change budget will be us

  1. Sharifi says:

    “A” is correct;
    The Project Board may also delegate decisions regarding changes to a Change Authority. PB decide whether to use a Change Authority and, if so, agree the level of authority to be delegated, page 267(C.1.1 General responsibilities)