Which one of the following is given as a reason for this?

According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the
start. Which one of the following is given as a reason for this?

PrepAway - Latest Free Exam Questions & Answers

A.
It can be difficult to predict the actual performance of resources

B.
All aspects of planning become more difficult the further into the future they extend

C.
Sufficient detail is only known once the relevant stage has begun

D.
The supplier is unlikely to comprehend the detailed schedule

One Comment on “Which one of the following is given as a reason for this?