Which of the following is NOT within the authority of the Project Board?

Which of the following is NOT within the authority of the Project Board?

PrepAway - Latest Free Exam Questions & Answers

A.
Approve the End Project Report

B.
Set Stage-level tolerance

C.
Approve Stage Plans

D.
Set project-level tolerance