PrepAway - Latest Free Exam Questions & Answers

When is the Risk Management Strategy produced?

When is the Risk Management Strategy produced?

PrepAway - Latest Free Exam Questions & Answers

A.
After authorization has been given to proceed with the initiation stage

B.
Before the planning of the initiation stage

C.
As soon as the Project Manager has been appointed at start-up

D.
After the Project Board have approved the Project Initiation Documentation

One Comment on “When is the Risk Management Strategy produced?