Can a baselined management product be changed once it has been approved?

Can a baselined management product be changed once it has been approved?

PrepAway - Latest Free Exam Questions & Answers

A.
No, change control is there to prevent changes

B.
Yes, there is no restriction

C.
Yes, but only if the users say so

D.
Yes, as long as it is agreed with the relevant authority before it takes place