Which is within the context of the Managing Product Delivery process?
A.
Receiving and signing off completed Work Packages
B.
Reviewing the work situation and triggering new Work Packages
C.
The continuing correct focus of the project should be confirmed at the end of each stage
D.
Demonstrate that each product meets its quality criteria through carrying out the specified
quality methods
Correct answer is D.
0
0
C
0
0
D is the correct one.
0
0
Correct answer is D. :MPD 16.3, 5th bullet point