Which is a responsibility of the Project Assurance role?

Which is a responsibility of the Project Assurance role?

PrepAway - Latest Free Exam Questions & Answers

A.
Inform the Project Manager about the status of the project’s products

B.
Document the Project Board’s reporting needs

C.
Ensure the Project Manager is aware of the need to use any existing corporate standards

D.
Inform corporate or programme management about the project’s status

6 Comments on “Which is a responsibility of the Project Assurance role?

  1. Rodrigo says:

    A, the Answer given is correct.

    Providing an independent view of how the project is progressing is the job of project assurance. In PRINCE2, there are three views of assurance:business, user and specialist. Each view reflects the interests of the three project board members.

    Assurance is about checking that the project remains viable in terms of costs and benefits (business assurance), checking that the users’ requirements are being met (user assurance), and that the project is delivering a suitable solution (specialist or technical assurance). On some projects, the assurance is done by a separate team of people called the project assurance team, but the assurance job can be done by the individual members of the project board themselves.




    0



    0
  2. Sharifi says:

    “B” is the correct answer:
    Anyone appointed to a Project Assurance role reports to the Project Board member overseeing the relevant area of interest, and must be independent of the Project Manager. The Project Board should not assign any Project Assurance roles to the Project Manager.5.3.23