Which PRINCE2 role has a specific responsibility for ensuring that the quality activities relating to
products at all stages has appropriate user representation?
A.
Project Manager
B.
Executive
C.
Project Assurance
D.
Quality Assurance
You must be logged in to post a comment.
Correct answer is C