If the Project Manager needs to know the results of a quality review, the [ ?

Identify the missing words in the following sentence. If the Project Manager needs to know the
results of a quality review, the [ ? ] will provide a summary together with the date of any follow-up
meeting.

PrepAway - Latest Free Exam Questions & Answers

A.
Stage Plan

B.
Issue Register

C.
Daily Log

D.
Quality Register

Explanation:
Reference:http://www.prince2primer.com/prince2-quality-theme/