what should happen first?

When it is forecast that one or more tolerances are to be exceeded, what should happen first?

PrepAway - Latest Free Exam Questions & Answers

A.
The next higher level of management will begin to execute management by exception

B.
The appropriate level of management must refer the matter to the next higher level

C.
The Project Plan will be replaced by a fallback plan

D.
The appropriate level of management will automatically produce and execute an Exception
Plan to recover from the deviation without referral