PrepAway - Latest Free Exam Questions & Answers

When does the Directing a Project process start?

When does the Directing a Project process start?

PrepAway - Latest Free Exam Questions & Answers

A.
On completion of the Starting up a Project process

B.
On completion of the Initiating a Project process

C.
When the Starting up a Project process commences

D.
After the project has been authorized

6 Comments on “When does the Directing a Project process start?

  1. Rodrigo says:

    The correct Answer is A:
    See page 135 of the PRINCE2 manual, section 13.3, as suggested by “PRINCE2 student,” or reference page 18 of PRINCE2 for Dummies.




    0



    0
  2. d3m0 says:

    Correct answer is A

    See “Managing successful projects with PRINCE2”
    Page 135, section 13.3

    The Directing a Project process starts on completion
    of the Starting up a Project process and is triggered
    by the request to initiate a project.




    0



    0

Leave a Reply