When should the Managing a Stage Boundary process be undertaken?

When should the Managing a Stage Boundary process be undertaken?

PrepAway - Latest Free Exam Questions & Answers

A.
Close to the end of a management stage

B.
After the completion of each management stage

C.
At the end of the final stage

D.
At the end of project start-up

9 Comments on “When should the Managing a Stage Boundary process be undertaken?

  1. Rodrigo says:

    D, the Answer given is Correct.

    This is because at the very least a project has to be divided into two stages. 1.The Startup, and 2.Rest of the Project. With this in mind, the stage Managing a Stage Boundary process has to be employed for the initial Startup before authorization to commence the project where the actual work is done is given.