What process covers the acceptance and execution of project work by external suppliers?
A. Controlling a Stage
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project
6 Comments on “What process covers the acceptance and execution of project work by external suppliers?”
Asays:
Correct answer is C. Controlling a Stage authorizes a work package but it is the Managing Product Delivery process that accepts, executes and delivers the work package.
2
0
peppesays:
i agree
0
0
Rodrigosays:
The correct answer should be C. The only three activities for “Managing Product Delivery” are to receive the Work Package, build the products, and then hand them back when the whole Work Package
0
0
Sharifisays:
“C” is the correct answer:related to the delivery;
Work Packages – pending authorization, in
execution, and completed in the period (if
the Work Packages are being performed
by external suppliers, this information may
be accompanied by purchase order and
invoicing data)
Correct answer is C. Controlling a Stage authorizes a work package but it is the Managing Product Delivery process that accepts, executes and delivers the work package.
2
0
i agree
0
0
The correct answer should be C. The only three activities for “Managing Product Delivery” are to receive the Work Package, build the products, and then hand them back when the whole Work Package
0
0
“C” is the correct answer:related to the delivery;
Work Packages – pending authorization, in
execution, and completed in the period (if
the Work Packages are being performed
by external suppliers, this information may
be accompanied by purchase order and
invoicing data)
0
0
c is correct