What process covers the acceptance and execution of project work by external suppliers?

What process covers the acceptance and execution of project work by external suppliers?

PrepAway - Latest Free Exam Questions & Answers

A.
Controlling a Stage

B.
Managing a Stage Boundary

C.
Managing Product Delivery

D.
Directing a Project

6 Comments on “What process covers the acceptance and execution of project work by external suppliers?

  1. Rodrigo says:

    The correct answer should be C. The only three activities for “Managing Product Delivery” are to receive the Work Package, build the products, and then hand them back when the whole Work Package




    0



    0
  2. Sharifi says:

    “C” is the correct answer:related to the delivery;
    Work Packages – pending authorization, in
    execution, and completed in the period (if
    the Work Packages are being performed
    by external suppliers, this information may
    be accompanied by purchase order and
    invoicing data)