The creation of an Exception Plan often follows which of the following situations?

PrepAway - Latest Free Exam Questions & Answers

A.
A time or cost slippage occurring during a management stage

B.
An Exception Report being submitted to the Project Board in the case of a management stage
being forecast to exceed its tolerance

C.
A Stage Plan updated due to an urgent corrective action being taken by the Project Manager

D.
A newly identified risk being captured and documented in the Risk Register