PrepAway - Latest Free Exam Questions & Answers

This would be in the respective Registers.)

Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but
the End Stage Report is not used to ‘capture and maintain’ information regarding issues and risks.
This would be in the respective Registers.)

PrepAway - Latest Free Exam Questions & Answers

A.
Capture and maintain information regarding issues and risks

B.
Document the project’s acceptance criteria

C.
Escalate a stage-level tolerance threat to the Project Board

D.
Give a summary of progress to date