For a project to start and carry on, a PRINCE2 principle states that a project must have [?]?

Identify the missing words from the following sentence… For a project to start and carry on, a
PRINCE2 principle states that a project must have [?]?

PrepAway - Latest Free Exam Questions & Answers

A.
Lesson applied throughout

B.
Continued business justification

C.
At least two stages

D.
Focus on products that will meet business expectations