Which of the following steps looks at the probability, impact and proximity of a risk?
A. Communicate
B. Assess (estimate)
C. Identify (context)
D. Plan
One Comment on “Which of the following steps looks at the probability, impact and proximity of a risk?”
Sharifisays:
“B” is the correct answer,
Page 82:
8.3.5.2 Assess (Estimate):
The primary goal of the ’Estimate’ step is to assess the threats and the opportunities to the project in terms of their probability and impact. The risk proximity will also be of interest to gauge how quickly the risk is likely to materialize if no action were taken.
“B” is the correct answer,
Page 82:
8.3.5.2 Assess (Estimate):
The primary goal of the ’Estimate’ step is to assess the threats and the opportunities to the project in terms of their probability and impact. The risk proximity will also be of interest to gauge how quickly the risk is likely to materialize if no action were taken.