Which product establishes the baseline against which the project’s actual performance is compared?
A. Project Brief
B. Product Status Account
C. Project Initiation Documentation
D. Configuration Item Record
4 Comments on “which the project’s actual performance is compared?”
Sharifisays:
Project plan provides a baseline against which to monitor
the project’s progress stage by stage
0
0
Sharifisays:
Project plan is used by the Project Board as a baseline against which to monitor project progress.
0
0
Sharifisays:
“A” is the answer:
A.19.1 Purpose
A Project Brief is used to provide a full and firm
foundation for the initiation of the project and is
created in the Starting up a Project process.
In the Initiating a Project process, the contents of
the Project Brief are extended and refined in the
Project Initiation Documentation, after which the
Project Brief is no longer maintained.
0
0
SbSsays:
C is the correct answer.
According to “Managing Successul Projects with Prince2” (see section A.20.1):
The three primary uses of the Project Initiation Documentation are to:
• Ensure that the project has a sound basis before asking the Project Board to make any major
commitment to the project
• Act as a base document against which the Project Board and Project Manager can assess
progress, issues and ongoing Viability questions
• Provide a single source of reference about the project so that people joining the ‘temporary
organization’ can qUickly and easily find out what the project is about, and how it is being
managed.
Project plan provides a baseline against which to monitor
the project’s progress stage by stage
0
0
Project plan is used by the Project Board as a baseline against which to monitor project progress.
0
0
“A” is the answer:
A.19.1 Purpose
A Project Brief is used to provide a full and firm
foundation for the initiation of the project and is
created in the Starting up a Project process.
In the Initiating a Project process, the contents of
the Project Brief are extended and refined in the
Project Initiation Documentation, after which the
Project Brief is no longer maintained.
0
0
C is the correct answer.
According to “Managing Successul Projects with Prince2” (see section A.20.1):
The three primary uses of the Project Initiation Documentation are to:
• Ensure that the project has a sound basis before asking the Project Board to make any major
commitment to the project
• Act as a base document against which the Project Board and Project Manager can assess
progress, issues and ongoing Viability questions
• Provide a single source of reference about the project so that people joining the ‘temporary
organization’ can qUickly and easily find out what the project is about, and how it is being
managed.