PrepAway - Latest Free Exam Questions & Answers

which the project’s actual performance is compared?

Which product establishes the baseline against which the project’s actual performance is
compared?

PrepAway - Latest Free Exam Questions & Answers

A.
Project Brief

B.
Product Status Account

C.
Project Initiation Documentation

D.
Configuration Item Record

4 Comments on “which the project’s actual performance is compared?

  1. Sharifi says:

    “A” is the answer:
    A.19.1 Purpose
    A Project Brief is used to provide a full and firm
    foundation for the initiation of the project and is
    created in the Starting up a Project process.
    In the Initiating a Project process, the contents of
    the Project Brief are extended and refined in the
    Project Initiation Documentation, after which the
    Project Brief is no longer maintained.




    0



    0
  2. SbS says:

    C is the correct answer.

    According to “Managing Successul Projects with Prince2” (see section A.20.1):
    The three primary uses of the Project Initiation Documentation are to:
    • Ensure that the project has a sound basis before asking the Project Board to make any major
    commitment to the project
    • Act as a base document against which the Project Board and Project Manager can assess
    progress, issues and ongoing Viability questions
    • Provide a single source of reference about the project so that people joining the ‘temporary
    organization’ can qUickly and easily find out what the project is about, and how it is being
    managed.




    0



    0

Leave a Reply