Which of the following is a purpose of the Managing a Stage Boundary process?
A.
Approve the next Stage Plan and review the updated Project Plan
B.
Co-ordinate an area of work that will deliver one or more of the project’s products
C.
Place formal requirements on accepting, executing and delivering project work
D.
Deal with issues and report progress to the Project Board
Confirm continued viability and acceptability of the risks
0
0
Ok
The purpose of the Managing a Stage Boundary process is to enable the Project Board to be provided with sufficient information by the Project Manager so that it can review the success of the current stage, approve the next Stage Plan, review the updated Project Plan, and confirm continued business justification and acceptability of the risks. Page 193
0
0
I agree with the answer. A
0
0
I believe this question is not properly formulated.
0
0
agreed
0
0
Approve the next stage plan is done by Project Board in DP.
Wrong Options Provided.