Which of the following is carried out as part of the Initiating a Project process?

Which of the following is carried out as part of the Initiating a Project process?

PrepAway - Latest Free Exam Questions & Answers

A.
Ensure there is authority to deliver the project’s products

B.
Ensure there is a common understanding of the reasons for doing the project

C.
Appoint the Executive and Project Manager

D.
Create a stage Plan for the next stage of the project