Which is a benefit of using PRINCE2?
A.
Stakeholders are kept out of planning and decision making
B.
Participants understand each other’s roles and needs
C.
Stakeholders are not involved in assuring the project work
D.
All problems are escalated to all stakeholders
I think the answer should be B – Participants understand each other’s roles and needs
(Please refer to section 1.7 in the PRINCE2 Manual)
1
0
i agree, correct answer is B
0
0
ok, “B” is the right answer.
0
0
This is the second question in this site that has given the wrong answer.
The people in the discussion are right.
Axelos (the people who produced the PRINCE2 manual) also said the answer is B.