According to PRINCE2, which of the following are the 6 aspects of project performance to be
managed?
A.
Processes, themes, principles, tailoring, tolerance, roles
B.
Time, cost, people, quality, progress, risk
C.
Time, cost, quality, scope, tolerance, benefits
D.
Time, cost, scope, quality, benefits, risk
I agree with the answer. D