Which of the following would be carried out as part of a post-project benefits review?

Which of the following would be carried out as part of a post-project benefits review?

PrepAway - Latest Free Exam Questions & Answers

A.
An assessment of whether the project fulfilled its original objectives

B.
A review of the performance of the project’s products in operational use and identification of
whether there have been any side-effects

C.
An assessment of the project’s risk management procedure

D.
A review of the performance of the project management method and the project management
team

One Comment on “Which of the following would be carried out as part of a post-project benefits review?

  1. Sharifi says:

    Ok
    B.
    A review of the performance of the project’s products in operational use and identification of
    whether there have been any side-effects (beneficial or adverse)