PrepAway - Latest Free Exam Questions & Answers

Which of the following statements are correct regarding tolerance?

Tolerance forms a key element of allowing the Project Board to manage by exception. Which of
the following statements are correct regarding tolerance?
1. The Project Board sets project tolerances
2. Tolerances can be applied for Time, Cost, Scope, Quality, Benefit and Risk
3. The Project Manager sets Work Package tolerance
4. Cost tolerance should not be used to pay for authorized requests for change

PrepAway - Latest Free Exam Questions & Answers

A.
1,2,3

B.
1,2,4

C.
1,3,4

D.
2,3,4

One Comment on “Which of the following statements are correct regarding tolerance?


Leave a Reply