According to PRINCE2, Project Board members would NOT be involved in which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Confirming project tolerances with corporate or programme management

B.
Authorizing the start of the project

C.
Running of the project on a day-to-day basis

D.
Communications between the project management team and stakeholders external to that
team