Which product would document any unfinished work, ongoing issues and risks?

Which product would document any unfinished work, ongoing issues and risks?

PrepAway - Latest Free Exam Questions & Answers

A.
Project closure notification

B.
Lessons Report

C.
End Project Report

D.
Risk Register