A risk consists of a combination of the of a perceived threat or opportunity occurring and the magnitude of it

Identify the missing word in the following sentence… A risk consists of a combination of the of a
perceived threat or opportunity occurring and the magnitude of its impact on objectives.

PrepAway - Latest Free Exam Questions & Answers

A.
Outcome

B.
Probability

C.
Dis-benefit

D.
Proximity

One Comment on “A risk consists of a combination of the of a perceived threat or opportunity occurring and the magnitude of it

  1. Sharifi says:

    Ok, see page 311
    Risk:
    An uncertain event or set of events that, should it occur,
    will have an effect on the achievement of objectives.
    A risk is measured by a combination of the probability
    of a perceived threat or opportunity occurring, and the
    magnitude of its impact on objectives.